A practical guide from a Dubai rigging and installation contractor for event agencies, production companies, exhibition builders, malls and venues planning temporary power for events, brand activations, festive lighting and seasonal installations in Dubai, Abu Dhabi, Sharjah and across the UAE.
Temporary power for an event in Dubai is planned in four steps: decide where the supply comes from, add up the loads, size the source with headroom, then design the distribution from the source to every load. The supply is either the venue’s own distribution boards, a generator arranged for the project, or both.
Generator size is worked out from the total load, not guessed. List every piece of equipment, convert the total to kVA (generators are rated in kVA, usually at a power factor of 0.8), allow for start-up currents and non-linear loads such as LED screens, and leave headroom. Then plan the distribution boards, cable routes, earthing, protection and testing.
For a quick, accurate quote, send the venue, the dates, an equipment list or technical rider with power ratings, and whether the venue supply is available. Redfox plans and installs temporary power for events as part of the same team that rigs and installs.
Generator sizing is a calculation, and an electrical engineer or competent electrician should confirm it. The general method:
Which approvals apply depends on the venue, the site and the scope. The list below is a general guide, not legal advice. Confirm the current requirements with the venue, the event organiser and the relevant authority.
Before switch-on, every circuit is inspected and tested: earthing, insulation, polarity and RCD operation. On the day, an electrician on standby can deal with faults and changes. Redfox prepares the power plan, method statements and risk assessments, and works with the venue, organiser or main contractor on the submissions.
Attach the rider, site plan or drawings to the quote form below, or send them on WhatsApp. See also the truss and chain hoist rental quote checklist if the event also needs rigging.
Power problems at events usually come from the gaps between contractors: a cable route that crosses a rigging zone, a hoist circuit nobody allowed for, or a distribution board in the wrong place. Redfox plans the temporary power, the rigging and the installation as one team, so loads, hanging points and cable routes are planned together.
Redfox is a Dubai technical contracting company founded in 2003. At The Galleria Mall in Abu Dhabi, we installed an illuminated ribbon across the facade, fixed to a live facade, rigged at height and powered with clean cable runs (case study). Inside the same mall, our crew rigged a structure of about 1.5 tons above the central atrium in 2 days (case study). We do the jobs others called not possible.
List every load with its rated power, add up the running load in kW, convert to kVA (at a power factor of 0.8, kVA is roughly kW divided by 0.8), allow for starting currents and non-linear loads such as LED screens, and leave headroom, commonly in the order of 20 to 25 percent. An electrical engineer or competent electrician should confirm the final size.
kW is the real power the equipment uses. kVA is the apparent power the generator has to supply. Generators are usually rated in kVA at a power factor of 0.8, so a generator’s kW capacity is roughly 80 percent of its kVA rating.
Often, yes. Most indoor venues, malls, hotels and exhibition halls provide power from their own boards. Ask the venue what supply is available at each point. Outdoor sites, and events whose load exceeds the venue supply, usually need a generator.
Distribution boards, cabling sized for the load and the run length, weatherproof connections, earthing, electrical protection such as RCDs and breakers, cable protection across walkways, labelling, and testing and commissioning before switch-on.
Usually. The venue or landlord sets the rules, and public events need event permits. Generators, fuel storage and fire safety can fall under Civil Defence requirements. Confirm the current requirements with the venue, the organiser and the relevant authority.
Redfox plans and installs the temporary power distribution and connects to the venue supply or to a generator arranged for the project. Tell us what the site has and we set out what is needed.
The venue and location, the dates and hours, an equipment list or rider with power ratings, whether venue power is available, whether a generator is needed, a site plan, which systems are show-critical, and whether you need an electrician on standby.
Send the site, the dates and what you need. We come back to you with a written quote, priced for your project.
Organisations we have worked with








Send the venue, the dates and the rider or equipment list. We come back with the power plan, what is needed on site and a written quote.